You can configure automatic flattening or flattening with user intervention for products and plans to automatically create multiple flattened structures. You can then use these structures in downstream data such as claims adjudication, or as data input to System for Electronic Rate and Form Filing (SERFF) files.

Pega Product Composer for Healthcare Pega Product Composer for Healthcare Pega Product Composer for Healthcare
The auto-flattening process automatically flattens new or updated products and plans when they have either Approved or Approved and hold status. The best practice is to automatically flatten products and plans with no manual intervention. However, based on your organization's business rules, you might want to flatten products and plans with user intervention.
  1. In the header of Dev Studio, click ConfigureProduct composer systemConfiguration.
  2. Click the Flow settings tab.
  3. In the Auto flatten settings section, configure the option that meets your organization's needs.
    ChoiceAction
    To follow the best practice and have flattening occur automatically with no user intervention
    1. In the Auto flatten settings section, select the Enable auto flattening check box to have flattening occur automatically.
      Note: Do not select the User action enabled for auto-flattening check box.
    2. In the Product stage list of auto-flatten section, select the stages in which you want auto-flattening to occur, for example, Production.
    3. Click Save.
    To have flattening occur automatically but with the option of specifying products or plans
    1. In the Auto flatten settings section, select the Enable auto flattening check box to have flattening occur automatically.
    2. Select the User action enabled for auto-flattening check box so that you can select the products or plans for auto-flattening.
    3. In the Product stage list of auto-flatten section, select the stages in which you want auto-flattening to occur, for example, Production.
    4. Click Save.
    To view the flattened results of updated product and the plans created from the product or the updated plan itself, see Viewing the auto-flattened entities below.
What to do next: You can package and export the flattened structure by using the Rule-Admin-Product (RAP) rule. For more information, see Moving applications between systems.

Configuring reattempt settings for auto-flattening

Configure settings for the number of times that Pega Product Composer for Healthcare attempts to flatten entities that have the Pending-Save status and the calculated time between attempts. Ensure that you allow enough time for the entities to move from the Pending-Save status to the Approved or Approved and hold status.

You can also configure settings for the email account that is used to alert users that entities continue to have the Pending-Save status and auto-flattening cannot proceed.
  1. In the header of Dev Studio, enter and search for FlatteningRequeueMaxAttempt.
  2. Click the Dynamic System Settings rule.
  3. On the Edit Dynamic Settings page, modify the value for the number of times that Pega Product Composer for Healthcare attempts to flatten a dependent entity that has the Pending-Save status.
  4. Click Save.
  5. In the header of Dev Studio, enter and search for FlatteningRequeueDelay.
  6. Click the Dynamic System Settings rule.
  7. On the Edit Dynamic Settings page, modify the value for the calculated time between reattempts.
    For example: If you configured the FlatteningRequeueMaxAttempt rule as 3 and the FlatteningRequeueDelay rule as 5, then the first attempt occurs immediately, the second attempt occurs 10 (2 x 5) seconds later, and the third and last attempt occurs 15 seconds later.
  8. Click Save.
  9. Optional: To configure the email account that is used to alert users that auto-flattening cannot proceed:
    1. In the navigation pane of Dev Studio, click RecordsIntegration-ResourcesEmail Account.
    2. On the Email Account page, click PegaPCS-HC-USA-Work and complete the fields.
      For more information, see Integrating with an email provider.
    3. Click Save.

Viewing the auto-flattened entities

Whenever you update a product or a plan, the auto-flattening process flattens the updated product and the plans that were created from the product or the updated plan itself. You can view the information that is related to this process.

  1. Log in to Dev Studio by entering your Pega Product Composer for Healthcare administrator credentials.
  2. In the header of Dev Studio, click Launch portalProduct Development.
  3. In the left navigation pane, click Process EntitiesUpdate
  4. Click the Auto flatten tab.
    The Auto flatten work ID column shows the ID of the plan that was automatically flattened. The Auto flatten source column shows the entity that was flattened.
  5. Click Auto-flatten status to generate a report.
    • Click Edit report to navigate to the reporting feature.
    • Click the Actions menu and then an item to format the report.

  • Previous topic Generating a flattened structure for plan and product data
  • Next topic Extracting Pega Product Composer for Healthcare data and generating reports

Have a question? Get answers now.

Visit the Support Center to ask questions, engage in discussions, share ideas, and help others.

Did you find this content helpful?

Want to help us improve this content?

We'd prefer it if you saw us at our best.

Pega.com is not optimized for Internet Explorer. For the optimal experience, please use:

Close Deprecation Notice
Contact us