Setting a goal and deadline for an assignment
You can set a goal and deadline for an assignment to automatically enforce your service-level agreements. By default, goal and deadline times are measured from the time that an assignment is routed to a worklist or work queue to the time that the assignment is completed.
- In the Explorer panel, click Case types, and then click the case type that you want to open.
- On the Workflow tab, click Life cycle.
- Click an assignment or approval step in a process.
- Click Goal & deadline.
- Select the Consider goal and deadline check box.
-
Define the criteria for the goal and deadline.
To define custom criteria:
- In the Service-level agreement list, select Custom.
-
In the
Goal
and
Deadline
sections,
enter values in the fields to define the suggested and required completion times for
the assignment.
Options include:
- Days
- Enter a positive integer.
- HH:MM:SS
- Enter a formatted string of positive integers that represent hours and minutes. For example, enter 04:15:30 to indicate that the goal is 4 hours, 15 minutes, and 30 seconds.
- Increase urgency by
- Enter an integer to add to the current urgency of the assignment.
To reuse criteria from an existing service-level agreement:
- In the Service-level agreement list, select Use existing.
- Press the Down Arrow key in the field that is displayed and select the name of a service-level agreement.
- Click Save.