Skip to main content


         This documentation site is for previous versions. Visit our new documentation site for current releases.      
 

Specifying that an application meet a compliance score by adding the Check guardrail compliance score task

Updated on December 13, 2021

You can use the Check guardrail compliance score task so that an application must meet a compliance score for the deployment to continue. The default value is 97, which you can modify.

To specify that an application must meet a compliance score, do the following steps:
  1. Do one of the following actions:
    • Click a task, click the More icon, and then click either Add task above or Add task below.
    • Click Add task in the stage.
  2. In the Task list, click Check guardrail compliance.
  3. In the Weighted compliance score field, enter the minimum required compliance score.
  4. Continue configuring your pipeline. For more information, see one of the following topics:
  • Previous topic Continuing or stopping a deployment by adding the Perform manual step task
  • Next topic Starting another pipeline by adding the Trigger deployment task

Have a question? Get answers now.

Visit the Support Center to ask questions, engage in discussions, share ideas, and help others.

Did you find this content helpful?

Want to help us improve this content?

We'd prefer it if you saw us at our best.

Pega.com is not optimized for Internet Explorer. For the optimal experience, please use:

Close Deprecation Notice
Contact us